7 Traceability Matrix

  In order to verify that the Data Requirements specified in DR-726 have been satisfied by this document the following traceability matrix is provided. DR-726 lists specified contents required in SOP01 under section 13.3. The following table cross-references the applicable section of SOP01 (this document) against the relevant 13.3 subsection number, with a brief identifying phrase.


 
 
Table 7.1: DR-726 Traceability to SOP01
3|c|Table 7.1. DR-726 Traceability to SOP01    
1|c|DR-726 1c|SOP01 1c|Description
1|c|Req't 1c|Section  
1. 1.4 Introduction
2. 2.1, 3.1 Instrument description
3. 2. Function descriptions at subsystem level
3.a 2.2.1 Optical Systems Design
3.b 2.2.2 Mechanical Systems Design
3.c 2.2.3 Thermal Systems Design
3.d 2.2.4 Power Design
3.e.1 2.3.1 Detector Description
3.e.2 2.3.2 Camera Design
3.e.3 2.3.6-7 Camera Signal Processing
3.e.4 " Camera Electronics
3.e.5 4.1 Camera Sensitivity
3.e.6 2.3.2 Camera Parameters
3.e.7 4.4 Camera Trend Analysis
3.e.8 4.4 Detector Calibrations
3.e.9 - Miscellaneous
3.f 3.2 Commanding
3.g 3.2 Data & Telemetry Processing
3.h 2.3.6-7 On-board Processors
3.i 2.3.3-5 Other Systems
4.a 4.3 Instrument Sensitivity Models
4.a 4.4 Flight Calibrations
4.b 3.2.3 Routine Command Sequences for Mode Changes
4.c 3.2.3 Routine Command Sequences for Observations
4.d 3.2.1 Good Practices
5. 4.4 Calibration Philosophy
6. 3.2.5 Near Real Time Monitoring
7. 3.2.6 Contingencies
8. 5. Ground Processing Algorithms
9. 3.2.4 Operational Constraints
10. 5.2 Ground Processing Science Data